Traffic bridge Dokkum (NL)

Good preparation is half the battle

In June 2026, the temporary (emergency) bridge at the Aalsumerpoortsbrug in Dokkum was successfully installed!

After months of preparation, the plan has proven itself in practice. The two bridge sections, each 27 meters long and 2.5 meters wide, were hoisted into place safely and on schedule using the 450-ton crane. A great result of the collaboration between Janson Bridging BV and Van Spijker Infrabouw B.V. and all parties involved on and around the project.

An impressive piece of craftsmanship where technology, logistics, and teamwork came together perfectly. #Proud of everyone who contributed to this!

Regional broadcaster RTV NOF has produced a nice report on the installation: ???? ​​https://lnkd.in/e3PQn8p2

Share on:

Project details

Solution
Plate girder bridge
Type
JSB
Total length
27 m
Road surface width
5 m
Weight
70 tons
Plate girder bridge